Renovation Update:  (photos will be posted next week)

  • The new bar is framed, faced and ready for the top;
  • The rough plumbing and electric for the bar are in place;
  • The new ladies room has been framed out and the rough plumbing and electric are in place;
  • The opening in the wall for the 12ft x 8ft door to the patio has been cut, framed and the steel beam installed;
  • City Inspections for the plumbing and electric are scheduled for Monday, 03/11/13;
  • The wall that was behind the old bar in the Kennedy Room has been extended to 23 ft. and sheet rocked to accommodate the shuffleboard.
  • The steel support posts have been encased in sheetrock and cover with stained plywood and trimmed with chair rail;
  • The light switches for the Kennedy Room have been relocated;
  • Some minor unexpected problems arose which delayed the work a little but were remedied by the Contractor;
  • Spackling the new sheetrock and patching all the holes and cracks in the walls;

Upcoming week we anticipate the following work to be accomplished:

  • Plumbing trenches will be filled with concrete;
  • Wall Wainscoting installed;
  • Granite bar top;
  • Complete inside wall of the bar;
  • Completing electric to the bar:
  • Finish installing ceiling grid:
  • Install  new duct work for the HVAC